Andvora
Operations Platform
MODE DEMO — DATA SIMULASI • Lini #04 • Profil PVC 3-Inch • Shift 1

Seluruh interaksi di bawah berjalan di browser Anda dengan data shift simulasi. Anda dapat mengubah tahapan, mencatat delay, dan menguji gerbang mutu QC.

MODUL UTAMA • CHANGEOVER & LOSS CONTROL•CO-20261012-04A•Cikarang Extrusion Plant #01

Lini #04 • Ekstrusi Pipa PVC Kaku (Ø 63–110 mm)

Tipe: DIE_AND_TOOLING_CHANGE•PVC-PIPE-63MM-SDR17-WHT → PVC-PIPE-110MM-SDR21-GRY•Shift 1
Lini Produksi & Target Setup:Lini #04 • Ekstrusi Pipa PVC Kaku (Ø 63–110 mm)Budget Waktu Standar: 45 Menit
Supervisor & Lead Operator:Budi Santoso / Agus Riyadi
Kesiapan Pre-Flight:5 / 5 Item Selesai (100%)
Produk Asal (Previous)PVC-PIPE-63MM-SDR17-WHTPVC Compound K-65 • Putih Standard
Target Baru (Next)PVC-PIPE-110MM-SDR21-GRYPVC Compound K-67 • Abu-Abu Industri
Tooling & KalibratorDie head Ø110 mm SDR21 + Pin Kalibrator 110Tipe: DIE_AND_TOOLING_CHANGE
Jadwal & ShiftShift 108.00 WIB

Checklist Kesiapan Eksternal (SMED Pre-Stop Verification)

Pastikan seluruh elemen eksternal siap sebelum mesin lama dihentikan untuk memangkas downtime internal.

✓ Seluruh syarat wajib terpenuhi. Lini siap dihentikan.
Andvora Changeover Control Engine v1.4 • Penyimpanan Lokal Aktif